Columbia
- Plans ordered by the date received
Received: 11/19/2008 - SAU SCIENCE AND TECHNOLOGY CENTER WATER IMPROVEMENTS, MAGNOLIA AR. ONE SET OF PLANS SUBMITTED, $347.20 FEE PD
Received: 10/7/2008 - COLUMBIA COUNTY LIBRARY FIRE PROTECTION PLANS, MAGNOLIA AR. SIX SETS OF PLANS SUBMITTED, $56.00 FEE PD
Received: 9/18/2008 - HWY 79, REPAINTING 1.0 MG ELEVATED STORAGE TANK, MAGNOLIA AR. ONE SET OF PLANS SUBMITTED, $500.00 FEE PD
Received: 9/18/2008 - 4" WATER MAIN EXTENSION, SHELBY LANE WATERLINE EXTENSION, MAGNOLIA AR. TWO SETS OF PLANS/SPEC SUBMITTED, $199.65 FEE PD
Received: 8/25/2008 - CITY OF MAGNOLIA PROPOSED 500,000 GAL STORAGE TANK AND HWY 79 PUMP STATION. TWO SETS OF PLANS SUBMITTED PER PROJECT, $500.00 FEE PD
Received: 7/8/2008 - SOUTHERN AR UNIV, MAGNOLIA EDA PROPOSAL. ONE REPORT SUBMITTED, NO FEES REQUIRED. (REBECCA DRAPER)