Agencies | Online Services | Policies

Submitter

Submitter: Lemons, TimOrganization: Lemons Engineering Consultants
Address: 204 Cherry StreetCity: Cabot
State: ARZip: 72023
Phone Number: (501) 843-5081E-Mail:

Project Information

Project ID: 55468Manager: Stone, Jeff
Received: 11/14/2005 12:00:00 AMDue: 11/24/2005
Logged: 11/14/2005Closed: 0
Classification: Sewer TreatmentStatus: Open
  
Summary:
WASTE WATER TREATMENT FACILITY SHANNON HILLS SALINE COUNTY LEMONS ENGINEERING 1 SET OF PLANS 1 SPECIFICATIONS 1 CALCULATIONS **NO CHECK**
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 11/14/2005Due: 11/24/2005
Date Completed: 11/22/2005
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 1/17/2006Due: 1/27/2006
Date Completed: 1/25/2006
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 1/18/2006Due: 1/28/2006
Date Completed: 1/26/2006
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 2/3/2006Due: 2/13/2006
Date Completed: 2/13/2006
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 4/7/2006Due: 4/17/2006
Date Completed: 4/17/2006
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 4/27/2006Due: 5/7/2006
Date Completed: 5/8/2006
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 5/19/2006Due: 5/29/2006
Date Completed: 5/23/2006
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 4/17/2007Due: 5/8/2007
Date Completed: 5/9/2007
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 6/26/2007Due: 7/13/2007
Date Completed: 7/12/2007
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 7/20/2007Due: 7/30/2007
Date Completed: 7/30/2007
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 8/15/2007Due: 8/25/2007
Date Completed: 8/20/2007
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 8/29/2007Due: 9/8/2007
Date Completed: 8/31/2007
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 9/13/2007Due: 9/23/2007
Date Completed: 9/19/2007
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 1/2/2008Due: 1/12/2008
Date Completed: 1/9/2008
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 10/15/2008Due: 10/25/2008
Date Completed: 10/17/2008
Description:
_
 
Assigned To: Faulkner, MacAction: Review, Comment and/or Approve
Date Assigned: 10/30/2008Due: 11/9/2008
Date Completed: 11/3/2008
Description:
_
 Back | Return to Plan Index Page | Return to Engineering Home | Explanation of Terminology