Submitter: MORSHED, MM | Organization: GarNat Engineering |
Address: 3825 Mt. Carmel Road | City: Bryant |
State: AR | Zip: 72022- |
Phone Number: (501) 408-4650 | E-Mail: tariqgarnat@gmail.com |
Project Information
Project ID: 131655 | Manager: Jake Chatman |
Received: 2/15/2024 12:00:00 AM | Due: 2/25/2024 |
Logged: 2/15/2024 | Closed: 2/27/2024 |
Classification: Water Improvemnts(Non-Subdiv.) | Status: Closed |
Summary: | |
Red River Crossing, Water Line Relocation Hwy 95, Van Buren County, Hwy 95, Between Clinton & Scotland**ONLINE** Fee $500 PD |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 2/15/2024 | Due: 2/25/2024 |
Date Completed: 2/15/2024 | |
Description: | |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 2/15/2024 | Due: 2/25/2024 |
Date Completed: 2/23/2024 | |
Description: | |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 2/23/2024 | Due: 2/26/2024 |
Date Completed: 2/23/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 222 | Action: Reminder to follow-up |
Date Assigned: 2/23/2024 | Due: 4/8/2024 |
Date Completed: 2/26/2024 | |
Description: | |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 2/26/2024 | Due: 3/7/2024 |
Date Completed: 2/26/2024 | |
Description: | |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 2/26/2024 | Due: 3/7/2024 |
Date Completed: 2/27/2024 | |
Description: | |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 2/27/2024 | Due: 3/1/2024 |
Date Completed: 2/27/2024 | |
Description: | |
Project manager has approved this project. |