Submitter
Submitter: Raabe, Milton | Organization: Milton Raabe PE |
Address: 130 Hillside Place | City: Hot Springs |
State: AR | Zip: 71901 |
Phone Number: (501) 262-0517 | E-Mail: |
Project Information
Project ID: 131207 | Manager: Jake Chatman |
Received: 12/28/2023 12:00:00 AM | Due: 1/7/2024 |
Logged: 12/28/2023 | Closed: 4/4/2024 |
Classification: Sewer Improvemnts(Non-Subdiv.) | Status: Closed |
Summary: | |
200 BLOCK OF LONGPOINT RD TWO INCH PRESSURE SEWER, HOT SPRINGS,AR. ONE SET OF PLANS SUBMITTED, $50.00 FEE PD |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 12/28/2023 | Due: 1/7/2024 |
Date Completed: 12/28/2023 | |
Description: | |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 12/28/2023 | Due: 1/7/2024 |
Date Completed: 1/3/2024 | |
Description: | |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 1/3/2024 | Due: 1/6/2024 |
Date Completed: 1/3/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 222 | Action: Reminder to follow-up |
Date Assigned: 1/3/2024 | Due: 2/17/2024 |
Date Completed: 1/11/2024 | |
Description: | |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 1/11/2024 | Due: 1/21/2024 |
Date Completed: 1/11/2024 | |
Description: | |
Response letter received 01/11/24 |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 1/11/2024 | Due: 1/21/2024 |
Date Completed: 1/22/2024 | |
Description: | |
Response letter received 01/11/24 |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 1/22/2024 | Due: 1/25/2024 |
Date Completed: 1/22/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 222 | Action: Reminder to follow-up |
Date Assigned: 1/22/2024 | Due: 3/7/2024 |
Date Completed: 3/19/2024 | |
Description: | |
30d1 letter mailed 03/19/24. -SF |
Assigned To: 222 | Action: Reminder to follow-up |
Date Assigned: 3/19/2024 | Due: 4/18/2024 |
Date Completed: 4/1/2024 | |
Description: | |
Emailed resubmittal 03/24/24. -SF |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 4/1/2024 | Due: 4/11/2024 |
Date Completed: 4/1/2024 | |
Description: | |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 4/1/2024 | Due: 4/11/2024 |
Date Completed: 4/4/2024 | |
Description: | |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 4/4/2024 | Due: 4/7/2024 |
Date Completed: 4/4/2024 | |
Description: | |
Project manager has approved this project. |