Submitter
Submitter: Menley, Wayne | Organization: Miller Newell Engineers, Inc. |
Address: PO Box 705 | City: Newport |
State: AR | Zip: 72112- |
Phone Number: (870) 523-6531 | E-Mail: wmenleyengr@aol.com |
Project Information
Project ID: 131206 | Manager: Glenn Greenway |
Received: 12/28/2023 12:00:00 AM | Due: 1/7/2024 |
Logged: 12/28/2023 | Closed: |
Classification: Water Improvemnts(Non-Subdiv.) | Status: Open |
Summary: | |
PRAUGHT WATER LINE EXTENSION, FULTON CO WATER. TWO SETS OF PLANS/SPECS SUBIMTTED, $358.00 FEE PD |
Assigned To: 231 | Action: Review, Comment and/or Approve |
Date Assigned: 12/28/2023 | Due: 1/7/2024 |
Date Completed: 1/3/2024 | |
Description: | |
Assigned To: 31 | Action: Supervisor Review |
Date Assigned: 1/3/2024 | Due: 1/13/2024 |
Date Completed: 1/8/2024 | |
Description: | |
Assigned To: 231 | Action: Finalize and Send Letter |
Date Assigned: 1/8/2024 | Due: 1/11/2024 |
Date Completed: 1/8/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 231 | Action: Reminder to follow-up |
Date Assigned: 1/8/2024 | Due: 2/22/2024 |
Date Completed: 1/29/2024 | |
Description: | |
Assigned To: 231 | Action: Review, Comment and/or Approve |
Date Assigned: 1/25/2024 | Due: 2/4/2024 |
Date Completed: 1/29/2024 | |
Description: | |
Assigned To: 31 | Action: Supervisor Review |
Date Assigned: 1/29/2024 | Due: 2/8/2024 |
Date Completed: 2/1/2024 | |
Description: | |
Assigned To: 231 | Action: Finalize and Send Letter |
Date Assigned: 2/1/2024 | Due: 2/4/2024 |
Date Completed: 2/1/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 231 | Action: Reminder to follow-up |
Date Assigned: 2/1/2024 | Due: 3/17/2024 |
Date Completed: 2/9/2024 | |
Description: | |
Assigned To: 231 | Action: Review, Comment and/or Approve |
Date Assigned: 2/7/2024 | Due: 2/17/2024 |
Date Completed: 2/9/2024 | |
Description: | |
Assigned To: 31 | Action: Supervisor Review |
Date Assigned: 2/9/2024 | Due: 2/19/2024 |
Date Completed: 2/12/2024 | |
Description: | |
Assigned To: 231 | Action: Finalize and Send Letter |
Date Assigned: 2/12/2024 | Due: 2/15/2024 |
Date Completed: | |
Description: | |
Project manager has approved this project. |