Submitter
Submitter: Alford, Jerome B. | Organization: Bond Consulting Engineers East, Inc. |
Address: 3683 State Highway 77 North | City: Marion |
State: AR | Zip: 72364 |
Phone Number: 870-739-2228 | E-Mail: bondengineering@hotmail.com |
Project Information
Project ID: 128671 | Manager: Glenn Greenway |
Received: 5/18/2023 12:00:00 AM | Due: 5/28/2023 |
Logged: 5/18/2023 | Closed: |
Classification: Water Improvemnts(Non-Subdiv.) | Status: Open |
Summary: | |
GRAND PRAIRIE REGIONAL WATER DISTRIBUTION DISTRICT, IMPROVEMENTS TO TAKE OVER WRIGHT-PASTORIA WATER ASSOCIATION, ONE SET OF PLANS/SPECS HAVE BEEN SUBMITTED, $500 FEE PD. |
Assigned To: 192 | Action: Review, Comment and/or Approve |
Date Assigned: 5/18/2023 | Due: 5/28/2023 |
Date Completed: 5/26/2023 | |
Description: | |
Assigned To: 31 | Action: Supervisor Review |
Date Assigned: 5/26/2023 | Due: 6/5/2023 |
Date Completed: 5/29/2023 | |
Description: | |
Assigned To: 18 | Action: Supervisor Review |
Date Assigned: 5/29/2023 | Due: 6/8/2023 |
Date Completed: 6/2/2023 | |
Description: | |
Assigned To: 192 | Action: Finalize and Send Letter |
Date Assigned: 6/2/2023 | Due: 6/5/2023 |
Date Completed: 6/5/2023 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 192 | Action: Reminder to follow-up |
Date Assigned: 6/5/2023 | Due: 7/20/2023 |
Date Completed: 6/27/2023 | |
Description: | |
Assigned To: 192 | Action: Review, Comment and/or Approve |
Date Assigned: 6/22/2023 | Due: 7/2/2023 |
Date Completed: 6/27/2023 | |
Description: | |
Assigned To: 31 | Action: Supervisor Review |
Date Assigned: 6/27/2023 | Due: 7/7/2023 |
Date Completed: 6/28/2023 | |
Description: | |
Assigned To: 18 | Action: Supervisor Review |
Date Assigned: 6/28/2023 | Due: 7/8/2023 |
Date Completed: 7/5/2023 | |
Description: | |
Assigned To: 192 | Action: Finalize and Send Letter |
Date Assigned: 7/5/2023 | Due: 7/8/2023 |
Date Completed: 7/17/2023 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 192 | Action: Reminder to follow-up |
Date Assigned: 7/17/2023 | Due: 8/31/2023 |
Date Completed: 8/4/2023 | |
Description: | |
Assigned To: 192 | Action: Review, Comment and/or Approve |
Date Assigned: 7/27/2023 | Due: 8/6/2023 |
Date Completed: 8/4/2023 | |
Description: | |
Comment letter and approval drafted. Waiting on reponse from ENG by 8/9/23 |
Assigned To: 31 | Action: Supervisor Review |
Date Assigned: 8/4/2023 | Due: 8/14/2023 |
Date Completed: 8/14/2023 | |
Description: | |
Comment letter and approval drafted. Waiting on reponse from ENG by 8/9/23 |
Assigned To: 18 | Action: Supervisor Review |
Date Assigned: 8/14/2023 | Due: 8/24/2023 |
Date Completed: 8/14/2023 | |
Description: | |
Assigned To: 192 | Action: Finalize and Send Letter |
Date Assigned: 8/14/2023 | Due: 8/17/2023 |
Date Completed: 8/16/2023 | |
Description: | |
Project manager has approved this project. |
Assigned To: 231 | Action: Review, Comment and/or Approve |
Date Assigned: 11/28/2023 | Due: 12/8/2023 |
Date Completed: 11/28/2023 | |
Description: | |
Assigned To: 31 | Action: Review, Comment and/or Approve |
Date Assigned: 11/28/2023 | Due: 12/8/2023 |
Date Completed: 11/28/2023 | |
Description: | |